Editorial Note: This article was rewritten using Artificial Intelligence (AI) based on original, verified sources. The accompanying images were upscaled with the assistance of AI. Any resemblance of figures in the images to real persons is entirely coincidental. Brands and logos depicted are the property of their respective owners and do not imply official endorsement or affiliation.
The long-anticipated extension of the T8 tramway, which will eventually link Saint-Denis to Paris, is moving forward. On Friday, November 20, 2026, Île-de-France Mobilités (IDFM) presented the latest developments of the project during a public meeting, setting a target for full operation by 2031.
Expanding the Network
The project, originally approved in 2019, aims to connect the current T8 line-which serves Épinay-sur-Seine, Villetaneuse, and Saint-Denis-to key transport hubs. The planned route will feature ten new stations, stretching from Saint-Denis Porte de Paris to Rosa Parks in Paris. This extension is designed to improve connectivity for the La Plaine and Stade de France districts, linking the line to the RER B, Metro line 12, and the RER E.
Urban Transformation and Infrastructure
A significant aspect of the project involves major urban changes. A new bridge will be constructed south of the existing structure at Rue Francis de Pressensé to accommodate both the tramway tracks and dedicated bicycle paths. Furthermore, the plan introduces a ‘garden street’ concept, which includes the pedestrianization of the Rue des Fillettes.
Environmental considerations have been a focal point of the planning process. While the project necessitates the removal of 190 of the 560 trees currently on the site, IDFM has committed to a comprehensive compensation plan. This includes planting 592 new trees and transplanting 12 existing ones, resulting in a net increase of 400 trees within the project area.
Project Timeline and Costs
The total estimated cost for the extension is 224 million euros. Construction is expected to follow a phased approach:
- 2027: Commencement of initial network diversion works.
- 2028: Official start of the main construction phase.
- 2031: Targeted date for the tramway’s entry into service.
The project will also result in a reduction of local parking, with approximately 288 spaces-three-quarters of the existing capacity-being removed on several streets, including Avenue Jeanne-d’Arc and Rue Danielle-Casanova.