Home Lyon-Turin Rail Link: Viviana Tunnel Boring Machine Advances Slowly, Raising Concerns

Lyon-Turin Rail Link: Viviana Tunnel Boring Machine Advances Slowly, Raising Concerns

Share
Share

Lyon-Turin Rail Link: Viviana’s Slow Crawl, a Symptom of Deeper Issues

The decision to undertake the Lyon-Turin high-speed rail link was hailed as a strategic move to connect France and Italy, fostering economic growth and shifting freight from road to rail. However, as of July 2026, the project is facing significant headwinds, epitomized by the glacial pace of the Viviana tunnel boring machine. Averaging a mere three meters per day, Viviana’s progress is not just a technical challenge; it’s a stark indicator of the project’s systemic issues, raising critical questions about its feasibility, cost-effectiveness, and ultimate success.

The Numbers Don’t Lie: Delays and Cost Overruns

The initial target for the Lyon-Turin rail link’s inauguration was 2015. Now, TELT, the Franco-Italian public company overseeing the project, has pushed the completion date to 2033 – an eighteen-year delay. This extended timeline also means missing the 2030 deadline set by Brussels for its trans-European transport network. The sheer scale of the delay is alarming, especially when considering the project’s current progress: only 20.5 kilometers of the 115 kilometers of twin tunnels have been excavated, along with 27.1 kilometers of auxiliary galleries. This represents barely a fifth of the main construction, nearly a decade into the project’s active phase.

Financially, the situation is equally grim. The project has already seen over 2.8 billion euros in contracts signed by June 2020, with an additional 3 billion euros committed for excavation on the French side. A damning report from the European Court of Auditors in January 2026 revealed a staggering 127% increase in overall project costs. Luxembourg’s audit highlighted the Lyon-Turin link as a prime example of strategic EU infrastructure projects plagued by chronic delays and massive budget overruns. This raises fundamental questions about financial oversight and the initial projections for such a monumental undertaking.

Geology, Politics, and the Unpredictable Alpine Terrain

The slow progress of Viviana, operating on the CO7 section at Saint-Martin-la-Porte, is attributed to the inherent complexities of Alpine geology. “Three meters per day is what the capricious, unpredictable Alpine geology allows,” states the report. This highlights the formidable natural challenges of tunneling beneath the Mont d’Ambin, between Modane and the Susa Valley. However, geological hurdles are only part of the story. Political blockages have also played a significant role in exacerbating delays and increasing costs.

In 2019, the Italian government, caught between the anti-project Five Star Movement and the pro-project League, temporarily halted tender calls. It took months, and the looming threat of European funding withdrawal, for Rome to restart the process. This political wrangling led to lost time, idle teams, and inevitably, escalating costs. While a dozen sites from Maurienne to Piedmont are now active, including significant progress at La Praz (CO6) and Villarodin-Bourget (CO5), the political and geological realities underscore the project’s vulnerability to external factors.

A Glimmer of Progress Amidst the Challenges

Despite the overarching concerns, there are signs of progress. On the French side, excavations continue at La Praz, where the thousandth blast for the base tunnel’s twin tubes has been completed. At Villarodin-Bourget, preparations are underway for the arrival of a first tunnel boring machine, with the initial kilometer of galleries connecting the base tunnel to logistical tunnels achieved in October 2025. In Saint-Jean-de-Maurienne, SNCF Réseau has laid rails on four main and service tracks, and the tender for the new international station, linking the trans-border section to the historic line, has been issued.

On the Italian side, Salbertrand serves as a central hub for excavated material, and preparatory work is ongoing at Torrazza Piemonte for receiving untreated spoil. A significant development is the operationalization of the Illaz excavated material treatment plant at the CO11 site, where extracted rocks will be sorted, treated, and reused. These developments demonstrate a persistent effort to advance the project, even if the overall pace remains a concern.

The Unanswered Question: 2033 and Beyond

The critical question remains: will the Lyon-Turin rail link genuinely be ready by 2033? TELT asserts it will, but the European Court of Auditors expresses doubt. On the ground, teams are advancing inch by inch, facing the relentless challenge of the mountain. The operational Villarodin ventilation shaft, the continuous operation of Viviana, and the proliferation of galleries are testaments to human endeavor. Yet, as the saying goes, the mountain often has the last word.

For the residents of Maurienne, the Lyon-Turin project holds the promise of improved connectivity, fluid rail traffic, and a modal shift from road to rail. For local officials, it’s a gamble on the future. For engineers, it’s a daily technical challenge. For Brussels, it’s a strategic project burdened by persistent delays. And for those observing Viviana’s slow excavation beneath the Alps, it serves as a humbling lesson: nature’s formidable power and the complexities of large-scale infrastructure projects often defy even the most ambitious timelines and budgets.

Source: https://www.lavoixdefrance.fr/actualites/lyon-turin-le-tunnelier-viviana-avance-a-3-metres-par-jour-loin-des-cadences-attendues-10216/

Share
Related Articles

The Traditional Order of French Dinner Courses

The French dinner is more than a meal; it is an experience...

What Is Unpasteurized Cheese in France?

In France, unpasteurized cheese means cheese made from raw milk-milk that is...

French Email Phrases: Professional Communication at Work

Writing professional emails in another language can be tricky. In French, a...

France Summer Weather and Travel Considerations

How warm is France in summer? Summer in France usually brings mild...

whysofrance.com
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.